County Highway W Reconstruction (Salem, Wisconsin)
CLIENT: Kenosha County
Clark Dietz provided engineering design services to realign approximately 2,300 feet of County Highway W in Kenosha County. The existing two-lane roadway had a sharp curve that tractor-trailers could not navigate without crossing into oncoming traffic. The new alignment addressed this issue and brought the roadway into compliance with current county truck highway standards.
The design also included wider shoulders. With the Fox River running alongside the roadway, the additional width created challenges for fitting the roadway slopes without affecting the river. Clark Dietz coordinated with the U.S. Army Corps of Engineers and Wisconsin Department of Natural Resources (WDNR) to address these impacts and permitting requirements.
Our team completed environmental studies, identified wetlands, evaluated potential contamination, and prepared permit applications. The work also included reviewing properties for potential eligibility for the National Register of Historic Places and evaluating the project’s effects on water quality.
Topographic surveys and soil investigations helped establish the conditions needed for design. Clark Dietz also coordinated with utility providers, supported public involvement, and prepared right-of-way plats showing the property needed for the improvements.
The team developed roadway plans at the 30%, 60%, and 90% design stages and prepared construction plans, specifications, and cost estimates. Together, these services supported a roadway alignment designed to better accommodate trucks while addressing the nearby river, environmental resources, and property needs.